在估值约1.3万亿美元的IPO之前,Anthropic已提前收购发电设备。图片来源:Aaron Schwartz/Bloomberg via Getty Images
9月下旬,投行派珀·桑德勒公司(Piper Sandler)在一份简短公告中表示,该公司曾担任圣安东尼奥设备供应商OnePWR Solutions的财务顾问,协助其以34亿美元的价格将发电平台出售给一家“前沿AI实验室”。
如今,这家AI实验室的身份已经揭晓。据《金融时报》报道,Anthropic正投入34亿美元,为其不断扩张的数据中心业务采购燃气发电机组。这也是迄今为止AI企业进行的最大一笔发电设备直接投资。
据《金融时报》报道,这笔交易涉及OnePWR Solutions提供的1.7吉瓦重型天然气发电机组。Anthropic已达成该笔交易,并将接手OnePWR此前与卡特彼勒(Caterpillar)签署的发电机采购承诺。该协议还包含了配套设备安装所需的工程设计与施工能力。预计这批发电机组将在未来两年内陆续交付。
与此同时,Anthropic正在筹备上市,已于9月向美国证券交易委员会(SEC)提交S-1招股书。招股书显示,公司在算力与基础设施方面的承诺支出总额约为9,009亿美元,涵盖采购承诺和租赁协议。其中,约4,516亿美元预计将在2030年前支出,其余大部分承诺将延续至2045年。根据公司11月提交的招股书修正案,在9月30日之后的12个月内,另有707亿美元到期应付。
Anthropic目前正寻求1.3万亿美元的上市估值,计划以每股70至78美元的价格发行8.25亿股股票。
招股书中还列出了Anthropic面临的几项核心风险,其中就包括采用天然气供电的数据中心。公司警告称,对天然气的依赖可能使数据中心建设面临能源价格波动的冲击。
招股书指出:“随着数据中心运营商对天然气发电的依赖日益加深,且受各地监管法规限制,表后发电和现场发电仅在部分地区可行,我们预计,在这些地区,不同用户对同一批天然气供应和管道输送能力的竞争将日趋激烈。”
Anthropic和OnePWR Solutions均未立即回应《财富》杂志的置评请求。
谋求更高的算力自主权
招股书中披露的各项支出承诺,表明Anthropic正全力保障自建算力供应,以满足开发和运行AI模型的实际需求。目前,公司的基础设施战略依赖多家技术供应商,包括亚马逊云科技(AWS)、谷歌云(Google Cloud)、英伟达(Nvidia)和超威半导体(AMD)。
不过,招股书还提出了一项名为“Anthropic Direct”的全新策略。按照这一模式,公司可直接租赁芯片,并将其部署在专用的数据中心内。招股书说明,这种做法使Anthropic能够把“数据中心容量承诺”与“内部部署的算力基础设施承诺”分开处理。
招股书解释道:“数据中心建设周期更长,但在总算力成本中占比较小。这种方式能让我们提前锁定数据中心容量,同时将规模更庞大的加速卡投资推迟,直到具体算力需求更加明确后再做决定。”
招股书同时明确指出,电力供应正成为制约公司业务扩张的核心瓶颈。Anthropic警告称,变压器、汽轮机、发电机、变电站等电力设备采购周期往往长达数年。设备制造商还面临价格上涨、关税以及产能受限等多重压力。与此同时,公司承认,为了获得交付周期较长的发电设备,可能不得不支付高于市场水平的价格。
Anthropic还特别披露,部分规划中的数据中心设施依赖专用天然气发电,这使公司面临燃料管线供应波动、管道容量受限以及天然气供应中断等潜在风险。
AI热潮本质是电力之争
尽管Anthropic刚达成了迄今规模最大的发电设备采购交易,但它并非唯一一家试图掌握自有发电能力的AI龙头公司。
2025年12月,谷歌(Google)母公司Alphabet以47.5亿美元收购能源开发商Intersect Power。此前,Intersect一直在与谷歌合作,将数据中心与新增发电设施同址共建。这笔交易使谷歌能够更好地掌握新发电产能上线的节奏。
埃隆·马斯克旗下的xAI也改用燃气轮机,为其位于田纳西州和密西西比州的Colossus数据中心供电,原因是现有电网接入无法提供足够电力。
与此同时,据米尔肯研究院(Milken Institute)称,Meta正在其俄亥俄州数据中心园区,与能源基础设施公司威廉姆斯(Williams)合作推进自备天然气发电项目,相关发电设备投资额约16亿美元。
微软(Microsoft)于2024年9月与星座能源(Constellation Energy)签署为期20年的购电协议,从宾夕法尼亚州三哩岛核电站购电,协议总金额达160亿美元。
亚马逊也通过与泰伦能源(Talen Energy)达成协议,为其数据中心保障电力供应。该协议涉及的数据中心园区位于宾夕法尼亚州萨斯奎哈纳核电站附近,由核能供电。
亚马逊云科技全球数据中心副总裁凯文·米勒当时在泰伦能源发布的新闻稿中表示:“我们正在进行该州历史上规模最大的私营部门投资,总额达200亿美元,将为当地带来1,250个高技能岗位和经济效益。同时,我们还将与泰伦能源合作,利用无碳能源为我们的基础设施供电。”(财富中文网)
译者:刘进龙
审校:汪皓
9月下旬,投行派珀·桑德勒公司(Piper Sandler)在一份简短公告中表示,该公司曾担任圣安东尼奥设备供应商OnePWR Solutions的财务顾问,协助其以34亿美元的价格将发电平台出售给一家“前沿AI实验室”。
如今,这家AI实验室的身份已经揭晓。据《金融时报》报道,Anthropic正投入34亿美元,为其不断扩张的数据中心业务采购燃气发电机组。这也是迄今为止AI企业进行的最大一笔发电设备直接投资。
据《金融时报》报道,这笔交易涉及OnePWR Solutions提供的1.7吉瓦重型天然气发电机组。Anthropic已达成该笔交易,并将接手OnePWR此前与卡特彼勒(Caterpillar)签署的发电机采购承诺。该协议还包含了配套设备安装所需的工程设计与施工能力。预计这批发电机组将在未来两年内陆续交付。
与此同时,Anthropic正在筹备上市,已于9月向美国证券交易委员会(SEC)提交S-1招股书。招股书显示,公司在算力与基础设施方面的承诺支出总额约为9,009亿美元,涵盖采购承诺和租赁协议。其中,约4,516亿美元预计将在2030年前支出,其余大部分承诺将延续至2045年。根据公司11月提交的招股书修正案,在9月30日之后的12个月内,另有707亿美元到期应付。
Anthropic目前正寻求1.3万亿美元的上市估值,计划以每股70至78美元的价格发行8.25亿股股票。
招股书中还列出了Anthropic面临的几项核心风险,其中就包括采用天然气供电的数据中心。公司警告称,对天然气的依赖可能使数据中心建设面临能源价格波动的冲击。
招股书指出:“随着数据中心运营商对天然气发电的依赖日益加深,且受各地监管法规限制,表后发电和现场发电仅在部分地区可行,我们预计,在这些地区,不同用户对同一批天然气供应和管道输送能力的竞争将日趋激烈。”
Anthropic和OnePWR Solutions均未立即回应《财富》杂志的置评请求。
谋求更高的算力自主权
招股书中披露的各项支出承诺,表明Anthropic正全力保障自建算力供应,以满足开发和运行AI模型的实际需求。目前,公司的基础设施战略依赖多家技术供应商,包括亚马逊云科技(AWS)、谷歌云(Google Cloud)、英伟达(Nvidia)和超威半导体(AMD)。
不过,招股书还提出了一项名为“Anthropic Direct”的全新策略。按照这一模式,公司可直接租赁芯片,并将其部署在专用的数据中心内。招股书说明,这种做法使Anthropic能够把“数据中心容量承诺”与“内部部署的算力基础设施承诺”分开处理。
招股书解释道:“数据中心建设周期更长,但在总算力成本中占比较小。这种方式能让我们提前锁定数据中心容量,同时将规模更庞大的加速卡投资推迟,直到具体算力需求更加明确后再做决定。”
招股书同时明确指出,电力供应正成为制约公司业务扩张的核心瓶颈。Anthropic警告称,变压器、汽轮机、发电机、变电站等电力设备采购周期往往长达数年。设备制造商还面临价格上涨、关税以及产能受限等多重压力。与此同时,公司承认,为了获得交付周期较长的发电设备,可能不得不支付高于市场水平的价格。
Anthropic还特别披露,部分规划中的数据中心设施依赖专用天然气发电,这使公司面临燃料管线供应波动、管道容量受限以及天然气供应中断等潜在风险。
AI热潮本质是电力之争
尽管Anthropic刚达成了迄今规模最大的发电设备采购交易,但它并非唯一一家试图掌握自有发电能力的AI龙头公司。
2025年12月,谷歌(Google)母公司Alphabet以47.5亿美元收购能源开发商Intersect Power。此前,Intersect一直在与谷歌合作,将数据中心与新增发电设施同址共建。这笔交易使谷歌能够更好地掌握新发电产能上线的节奏。
埃隆·马斯克旗下的xAI也改用燃气轮机,为其位于田纳西州和密西西比州的Colossus数据中心供电,原因是现有电网接入无法提供足够电力。
与此同时,据米尔肯研究院(Milken Institute)称,Meta正在其俄亥俄州数据中心园区,与能源基础设施公司威廉姆斯(Williams)合作推进自备天然气发电项目,相关发电设备投资额约16亿美元。
微软(Microsoft)于2024年9月与星座能源(Constellation Energy)签署为期20年的购电协议,从宾夕法尼亚州三哩岛核电站购电,协议总金额达160亿美元。
亚马逊也通过与泰伦能源(Talen Energy)达成协议,为其数据中心保障电力供应。该协议涉及的数据中心园区位于宾夕法尼亚州萨斯奎哈纳核电站附近,由核能供电。
亚马逊云科技全球数据中心副总裁凯文·米勒当时在泰伦能源发布的新闻稿中表示:“我们正在进行该州历史上规模最大的私营部门投资,总额达200亿美元,将为当地带来1,250个高技能岗位和经济效益。同时,我们还将与泰伦能源合作,利用无碳能源为我们的基础设施供电。”(财富中文网)
译者:刘进龙
审校:汪皓
In late September, investment banking company Piper Sandler released a short memo saying it had served as a financial advisor for San Antonio-based equipment supplier OnePWR Solutions on its $3.4 billion sale of its power generation platform to a “frontier AI lab.”
Now, the AI lab in question has been revealed. Anthropic is committing $3.4 billion to secure gas-fired power generators for its expanding data center operations—the largest direct investment in power generation equipment by an AI company, according to the Financial Times.
The deal involves 1.7 gigawatts of heavy-duty natural gas generators from OnePWR Solutions, according to the FT. Anthropic agreed to the transaction, taking over generator commitments that OnePWR had previously made with Caterpillar. The arrangement also includes engineering and construction capabilities necessary to install the equipment. The generators are expected to become available in the next two years.
Meanwhile, Anthropic is preparing for its IPO, with the company filing its S-1 with the SEC in September. In the registration statement, Anthropic disclosed approximately $900.9 billion in aggregate committed spending on computing and infrastructure, which would include purchase commitments and lease agreements. Of that amount, about $451.6 billion is expected to be spent before 2030, with most of the remaining commitments extending through 2045. Another $70.7 billion is due within the 12 months following Sep. 30, according to the amended S-1 filed in November.
The company is seeking a $1.3 trillion valuation, selling 825 million shares at a range of $70 to $78 a piece.
The S-1 also outlined key concerns for Anthropic, of which gas-powered data centers were included. The company warned that the dependence on natural gas could put the data center buildout under threat of volatile prices.
“As data center operators increasingly rely on natural gas-fired generation, and because behind-the-meter and on-site arrangements are feasible only in some jurisdictions given the applicable regulatory frameworks, we expect increased competition among users for the same natural gas supply and pipeline capacity in those areas,” the filing read.
Anthropic and OnePWR Solutions did not immediately respond to a request for comment from Fortune.
Looking for more autonomy
The commitments outlined in Anthropic’s S-1 reflect the company’s effort to secure its own computing capacity needed to develop and operate its AI models. Currently, Anthropic’s infrastructure strategy spans several technology suppliers including Amazon Web Services, Google Cloud, Nvidia, and AMD.
But the S-1 describes a strategy called “Anthropic Direct,” in which the company can lease chips directly and place them in dedicated data centers on its behalf. According to the filing, it allows Anthropic to separate its “commitments for data center capacity” from its “commitments for the compute infrastructure deployed inside them.”
“Because data centers require longer lead times but represent a smaller fraction of total compute costs,” the S-1 reads, “this approach enables us to secure data center capacity early while deferring larger accelerator investments until our specific compute needs are more certain.”
The filing also makes it clear electricity and power are becoming a major constraint on that expansion. Anthropic warned that transformers, turbines, generators, substations, and other electrical equipment can take years to procure, with manufacturers facing higher prices, tariffs and limited production capacity. Alongside those concerns, the company also acknowledged it may need to purchase long-lead-time power generation at prices above market rates.
Anthropic specifically disclosed that some planned data center facilities rely on dedicated natural gas-fired generation, exposing it to fluctuations in fuel lines, pipeline capacity constraints, and disruptions to natural gas supplies.
The AI boom is really a power boom
While Anthropic just agreed to the largest acquisition deal for power generation equipment as of yet, it’s not the only AI-forward company looking to secure its own power generation.
In December 2025, Alphabet—the parent company of Google—acquired energy developer Intersect Power for $4.75 billion. Intersect had been working with Google to colocate data centers with new electricity generation, and the deal gave Google greater control over how quickly it could bring new power generation online.
Elon Musk’s xAI also turned to natural gas turbines to power its Colossus data centers in Tennessee and Mississippi after the existing grid connections couldn’t provide sufficient power.
Meanwhile, Meta has pursued on-site natural gas generation for its Ohio data center campus, working with energy infrastructure company Williams on a project worth approximately $1.6 billion in energy generation equipment, according to the Milken Institute.
And Microsoft signed a 20-year agreement with Constellation Energy in September 2024 to purchase electricity from the Three Mile Island nuclear facility in Pennsylvania, a $16 billion agreement.
Amazon has also pursued data center energy capacity through an agreement with Talen Energy, a nuclear-powered data center campus adjacent to the Susquehanna nuclear power plant in Pennsylvania.
“We’re making the largest private sector investment in state history–$20 billion–to bring 1,250 high-skilled jobs and economic benefits to the state, while also collaborating with Talen Energy to help power our infrastructure with carbon-free energy,” AWS Vice President of Global Data Centers Kevin Miller, said in a Talen Energy press release at the time.